Hi all What sort of labour time should a preventative change of above incur? Many Thanks
- posted
16 years ago
Hi all What sort of labour time should a preventative change of above incur? Many Thanks
autodata says just over 3 hours
Many thanks Jon.
Yes it should take under three hours, provided the 10mm heads on the bolts do not get rounded off when taking them out. These are the most stupid bolts I have come across and the steel material seems to be soft as well. The head is smaller than the size you would expect for this size of thread. Gets some spare ones in case you have problems.
Grff